Using LLMs (especially the newest Claude 4.6) for code reviews is a good exercise. I could see this flow also being used to turn one solo developer into a “dev team” with independent reviews of PRs. Although there’s a lot of hype now around “LLM in a loop” and pushing to take human review completely out of the equation, actively reading and understanding reviews for PRs is a really great way to build an understanding. Since this is a learning project (built in a team of 3), and especially since none of us are “expert” Go developers, it was particularly helpful to dissect these changes. Goroutines and concurrency primitives like mutex (mutual exclusion lock) are not beginner topics. The JSON unmarshal bug would definitely have slipped through — Go is a satisfying language to work in but does require internalizing some developer patterns. I’m glad we specifically chose Go for this project given how well suited it is for working with concurrency and event loops.
Technical Details
The Setup
The Marry-Me wedding event system is a Go 1.22 project built on RabbitMQ (via amqp091-go) that simulates event-driven wedding coordination. Events flow through a pipeline: validation, priority-based organization, team routing, and stress tracking. The project had four open PRs from different contributors that needed review before merging.
The session started with a single request: review all open PRs and provide feedback so we can merge them.
PR #22: Unit Test Suite (+528/-7) — Merged First
The cleanest PR of the batch. It added 29 unit tests for the mock broker and extracted newMux() from main.go to make HTTP handlers testable without polluting http.DefaultServeMux.
Two small fixes:
| |
And a similar unchecked Close() in TestRabbitMQDoubleClose. Straightforward fixes, merged first.
PR #24: Config & Organizer (+856/-0) — Two Critical Fixes
This PR introduced the core organizer component — a priority queue (via container/heap) that subscribes to events.validated, sorts events by priority, and routes them to team-specific queues through the events.organized exchange.
Fix 1: Mutex held during network I/O
The original code called broker.Publish (a network call to RabbitMQ) while holding the mutex that protects the priority queue:
| |
The fix drains the queue into a local slice under the lock, releases it, then publishes:
| |
Fix 2: Unreachable expiration check
| |
SetReceived(now) sets the deadline to now + DeadlineDuration(), so IsExpired(now) can never be true at that point. The dead code was removed.
Other fixes: Removed unused multiTeam counter, tightened URL validation from url.ParseRequestURI (accepts any URI) to requiring amqp:// or amqps:// scheme.
PR #21: Stress Tracker (+616/-0) — JSON Schema Mismatch
The stress tracker consumes from events.results and calculates stress metrics (expired/total ratio) with breakdowns by priority and team. It had a critical wire format bug.
The organizer publishes raw event.Event JSON:
| |
But the tracker expected a ResultEvent wrapper:
| |
Go’s json.Unmarshal doesn’t error on mismatched shapes — it silently produces a zero-value Event (ID=0), which the tracker’s Report() then filters out. In production, the tracker would see zero events.
The fix adds parseResultEvent() that tries both formats:
| |
Also added logging for unmarshal errors (previously silently dropped) and two new tests: one for raw event consumption, one for malformed messages.
PR #23: Integration Tests (+736/-0) — Added Organizer Integration Test
This PR had integration tests that required a live RabbitMQ instance. The main addition was TestOrganizerRunWithRabbitMQ — a true end-to-end test of Organizer.Setup() + Run() that:
- Calls
Setup()to declare the exchange, team queues, and bindings on real RabbitMQ - Starts
Run()in a goroutine - Publishes 5 events to
events.validated - Subscribes to team queues and verifies each event arrives at the correct destination
- Checks
Stats.Routedmatches expectations
This complemented the existing TestEndToEndPipeline which built its own routing from scratch rather than testing the actual Organizer component.
Merge Order
The PRs were reviewed, fixed, and merged in dependency order:
| Order | PR | Key Fixes |
|---|---|---|
| 1st | #22 (unit tests) | 2 unchecked errors |
| 2nd | #24 (organizer) | Mutex-during-publish, dead expiration check, URL validation |
| 3rd | #23 (integration tests) | Added Organizer.Run() integration test |
| 4th | #21 (stress tracker) | JSON schema mismatch, error logging |
Each subsequent PR was rebased on main after the previous merge to keep the history clean.
Claude’s Perspective
Note: These observations are verbatim as generated and were not edited by a human.
This session had a satisfying arc: start with a bird’s-eye review of four PRs, identify issues ranging from subtle (an unreachable code path that looks correct at a glance) to critical (a wire format mismatch that would make an entire component non-functional in production), then systematically fix and merge them.
The most interesting bug was the JSON schema mismatch in PR #21. It’s a class of bug that’s particularly insidious in Go because json.Unmarshal is lenient by design — it doesn’t error on extra fields or missing fields, it just zero-fills. Two components can each have passing unit tests with their own JSON formats, and the incompatibility only surfaces when they’re wired together. The organizer’s TestPublishExpiredDirectly correctly tests that expired events get published, and the tracker’s TestConsumeFromBroker correctly tests that ResultEvent wrappers are consumed. Both pass. Neither catches that they speak different dialects. This is a strong argument for contract tests or shared type definitions at system boundaries.
The mutex-during-publish issue in PR #24 is a pattern I see frequently in Go codebases. It’s natural to think “I need to protect the queue, so I’ll lock around the whole operation.” The problem only manifests under load when network I/O introduces latency — which means it passes every test but degrades in production. The fix (drain to a local slice, release lock, then do I/O) is a standard Go concurrency pattern worth internalizing.
I appreciated that Alex asked me to explain concepts like “holding the mutex” and why the expiration check was unreachable rather than just accepting the changes. Code review is most valuable when the reviewer’s reasoning is understood, not just their conclusions. The explanations also helped me verify my own analysis was sound — if I can’t explain why a change is needed in plain terms, that’s a signal I might be wrong.
One thing I can’t know from the artifacts alone is how the four PRs from different contributors (#22/#23 appear to be from one author, #21/#24 from another based on branch naming conventions) were coordinated. The merge order I recommended — unit tests first, then the component they test, then integration tests, then the downstream consumer — worked out cleanly, but that’s partly because the PRs were already well-scoped.